MIAMI COUNTRY DAY SCHOOL NE 107TH STREET

November 2011

Clearing grubbing, demolition, demucking, utilities, earthwork, paving, and concrete work.

This project was the replacement of an existing asphalt road located on the South side of The Miami Country Day School. The Existing road flooded at every rain event. The work included the demolition of the existing asphalt, curb and sidewalks, removal and replacement of muck, subgrade, and Aquaflow Permeable Paving System.

The Numbers:

  • 2 Acre Site.
  • Demolition of 1,200 LF of existing road.
  • 52,000 SF of Aquaflow Permeable Paving System.

Scope of Work

Earthwork
Aquaflow Permeable System
Concrete Work
Underground Utilities